3.10.11

HYBIOS 4.0/ Modeling Construction Logistics

After working with the shell prototypes using building scale materials, the construction logistics started  to become clearer. It became apparent that we needed to push the material upwards and tension it down, instead of using the cubic frame we used before. 


We devised a construction system, similar to Mechano toys, where the components of the system could be adjusted for height and angle to create differentiated variable spaces.






The result of the interior finish turned out a bit rough, but the system works so far. The fabric sagged while drying, due to some faults in the design of the system. It was also hard to finish and cut some elements inside. We plan on fixing those problems while working out the next prototype.